Answer:
B) Positive 5 days slack.
Step-by-step explanation:
The computation of the number of slacks in the project is
= Total completion time on a project - Task A planned days - Task B planned days - Task C planned days
= 25 days - 7 days - 5 days - 8 days
= 5 days slack
Basically we deduct the total planned days taken by each task from the total completion time on a project so that the number of slacks has come.