If an organization or subcontractor has performed similar projects in the past and has kept records of how long specific activities actually took, these historical data

can be used as a guide in estimating the durations of similar activities for future projects. (T/F)

User Candlejack
by
5.5k points

1 Answer

6 votes

Answer: True

Step-by-step explanation:

The previous or similar projects would be a better reference when considering a new project and the new project would be at advantage because mistakes and errors made from previous project would be avoided in the new project.