A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Given the above scenario, which of the following is correct?There are four paths in this network. (T/F)

User Mukwux
by
3.2k points

1 Answer

0 votes

Answer:

True

Step-by-step explanation:

There are four paths in this network. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Given the above scenario