He ____________ may include a high-level WBS in a graphic chart format or as an indentured list of the work elements and associated deliverables.

a) statement of work
b) project scope
c) document network
d) diagram work
e) breakdown structure

User Whirl Mind
by
5.1k points

1 Answer

4 votes

Answer:

The correct option is a that is a statement of work. The work breakdown structure must include the statement of task.A statement of work is a document in project management. It is referred to as a description of project work; It defines the project-specific activities. The statement of work also includes detailed pricing and important for the request of the proposal.

Step-by-step explanation:

Work break down structure is a system that breaks a project into smaller components. Work break down structure provides a framework for cost estimation and schedule development and control. Work break down structure include a statement of work

A statement of work include

  • The purpose of the project
  • Scope of work
  • location of work
  • allowable time for projects
  • Scheduling
  • deliverable milestone
  • Determination of goods and services
  • Specifies the hardware and software