Answer:
Question 1
a) yes
b) 5,900 direct labor x .67 rate = 3,953 dollars
Question 2
Work in process: 13,053
Step-by-step explanation:
Taking job V as a template we can solve for the predeterminate overhead rate:
9,600 direct labor
generates 6,432 overhead:
6,432/9,600 = 0.67
eahc dollar is charged with $0.67 overhead
Total cost accumulated for Job W:
3,200 raw materials
5,900 direct labor
3,953 overhead
13,053 total cost. As it is not compelte It will be considered work in process.