Answer:
Product V91Z overhead: $12,614.93
Product V21I overhead: $ 9,050.44
Missing Information:
Product V91Z Product V21I
Number of batches 70 13
Number of customer orders 21 10
Number of assembly hours 493 698
Question
Overhead per product using ABC method
Step-by-step explanation:
We multiply the activity rate of each activity with the level for each product.
Then, we add all three cost together to get the total overhead per product.
Product V91Z
70 x $84 + 21 x $75.15 + 493 x $10.46 = $12,614.93
Product V21I
13 x $84 + 10 x $75.15 + 698 x $10.46 = $9,050.44