You are a new Scrum Master and the Scrum team is about to start their very first sprint. What guidance should you provide on what they should produce in Sprint One

User Arasa
by
4.8k points

1 Answer

2 votes

The correct answer is The Team should produce a potentially-shippable component or functionality.