Answer:
Instructions are listed below
Step-by-step explanation:
Giving the following information:
The predetermined overhead rate:
Assembly and Testing= $15.00 per direct labor-hour
Packaging= $11.00 per direct labor-hour
The company’s direct labor wage rate is $18.00 per hour.
Job N-60:
Assembly Testing & Packaging
Direct materials $360 $33
Direct labor $117 $45
A) We need to use the following formula:
total cost= direct material + direct labor + manufacturing overhead
First, we need to determine the number of direct hours used:
Assembly= 117/18= 6.5 hours
Packaging= 45/18= 2.5 hours
total cost= (360 + 33) + (117 + 45) + (6.5*15 + 2.5*11)= $680
B)
Unitary cost= 680/10= $68