229k views
2 votes
Riverside Manufacturing designs and manufactures bathtubs for home and commercial applications. Riverside recorded the following data for its commercial bathtub production line during the month of​ March:

Standard DL hours per tub 5
Standard variable overhead rate per DL hour $ 4.50
Standard variable overhead cost per unit $ 22.50
Actual variable overhead costs $ 30,375
Actual DL hours 4,050
Actual variable overhead cost per machine hour $ 7.50
Actual tubs produced 1,000
1. What is the variable manufacturing overhead rate variance in​ March?

User VorganHaze
by
3.3k points

1 Answer

6 votes

Answer:

Step-by-step explanation:

Variable MOH rate variance = Actual Hours × (Actual Rate - Standard Rate)

= 4050 × ($7.50 - $4.50)

= 12150

User George Gao
by
3.3k points