How is shaft method carried out​

User Lamrin
by
8.0k points

1 Answer

2 votes
The method consists in drilling the holes and then injecting a slurry of water and cement under pressure through the holes till they are completely sealed off. In the past injection was done at low pressures like 6 kgf/cm2 but it has been proved that high pressure of the order of 300 kgf/cm2 can be used successfully