In order to avoid project delays, project managers confronted with a resource overload will seek to delay some of the noncritical activities by an amount no more than their slack period, to level the demand for that worker.

a. True
b. False

User Xcsob
by
4.2k points

1 Answer

4 votes

Answer: True

Explanation:

When a project manager is confronted with resource overload, an activity that is not on the critical path can be delayed in order not to unnecessarily delay the project. The non-critcal activities can be delayed than an amount no longer than the slack period. This levels demand for that worker.