166k views
1 vote
Most projects will employ bottom-up estimating at some point to serve as a basis for estimating cash flow needs and for controlling the project.

True

False

User Arunkvelu
by
8.4k points

1 Answer

2 votes

Answer:

The statement is TRUE

User Redwyre