Labor productivity = Total output/ Total Input
Labor rate = $10. Labor hours = 1,000
So total labour input = 1,000*10= 10,000.
Materials and energy cost input = 2000+500
⇒ total input = 10,000+ 2000+500= 12500
Total output (units produced) = 10,000
Labor productivity= 10,000/12500= 0.80