Resource leveling is a network scheduling technique that seeks to assign nearly equivalent work units to each member of the project team True False

User Hsgubert
by
4.1k points

1 Answer

1 vote

Answer:

False

Step-by-step explanation:

Resource leveling in project management is a technique used to ensure that over-allocation of resource or conflicts as a result of over-allocation does not occur.

Cheers