It takes 54 minutes for 4 people to paint 6 walls. How many minuets does it take 6 people to paint 7 walls?

User Derrik
by
7.9k points

1 Answer

5 votes

It takes 42 minutes for 6 people to paint 7 walls

Solution:

It takes 54 minutes for 4 people to paint 6 walls

To find: Minutes required for 6 people to paint 7 walls

If
M_1 men can do
W_1 work in
D_1 days working
H_1 hours per day and
M_2 men can do
W_2 work in
D_2 days working
H_2 hours per day, then


(M_1D_1H_1)/(W_1) = (M_2D_2H_2)/(W_2)

M = Number of men

D = Number of days

H = Number of hours per day

W = Amount of work

Here in this sum,

54 minutes for 4 people to paint 6 walls


H_1 = 54 minutes ; M_1 = 4 people ; W_1 = 6 walls

Minutes required for 6 people to paint 7 walls


H_2 = ? ; M_2 = 6 people ; W_2 = 7 walls

Substituting the values in formula, we get


(54 * 4)/(6) = (H_2 * 6)/(7)\\\\9 * 4 = (H_2 * 6)/(7)\\\\H_2 = (36 * 7)/(6)\\\\H_2 = 42

Thus it takes 42 minutes for 6 people to paint 7 walls