Complete Question:
When the contracting officer signs a contract that, in fact, indicates the contracting officer has made an affirmative determination that:
a The contractor has a satisfactory record of integrity and business ethics.
b The contractor is technically capable of completing the contract.
c All of the above.
d The contractor can obtain the adequate financial resources to perform the contract.
Answer:
When the contracting officer signs a contract it means that he made a affirmative determination of all the above mentioned statements.
Step-by-step explanation:
A contract officer usually signs a contract in order to make sure that has a satisfactory record of integrity and business ethics that are required in that particular field work. And it also means that he has agreed with all the terms and condition mentioned in that contract.
It also denotes that he has the capacity to technically complete the contract and also has all the financial needs to successfully complete it. Hence by considering all these explanation we can conclude that option C is the correct answer .