Answer:
v = 1779 veh/h
Step-by-step explanation:
We will calculate the peak hour volume by using the following formula:-
Vp = v / ( PHF)(N)(Fg)(Fhv)
here,
1. v is the peak hour volume
2. vp is the analysis flow rate
3. PHF is the peak hour factor
4. N is the number of lanes
5. Fg is the grade adjustment factor which is 0.99 for rolling terrain > 1200 pc/h/ln
6. Fhv is the heavy vehicle adjustment factor
vp = v / (PHF) (N) (Fg) (Fhv)
1250 = v / (0.84)(2)(1)(0.847)
v = 1779 veh/h