Answer:
Lumpy demand is not used in project management.
The correct answer is D
Step-by-step explanation:
Dummy is a zero activity, which helps in network analysis.
Activity refers to a task in network analysis.
Latest finish time is the latest completion time of a project in network analysis.
Lumpy demand refers to low demand as a result of higher cost. It is not used in network analysis (project management)