Andrew is the prom committee chairman. He is at the prom and realizes that the meal delivered to the attendees was steak and not chicken. Andrew makes the catering manager aware immediately that the chicken meal was agreed upon, so the steak meal is outside the project scope. Which project management process stage is Andrew in?

1 Answer

3 votes

Answer:

monitoring and controlling

Step-by-step explanation:

The five stages in the project management process are:

  1. Project initiation
  2. Project planning
  3. Project execution
  4. Project monitoring and controlling: in this stage you must measure the project's performance in order to identify any possible deviation from the project's plan. Project managers should use key performance indicators (KPI) to determine if the project s on track or not. In this case, one KPI was chicken meal and the deviation was steak meal.
  5. Project closure