A mass of 9 kilograms is lifted through a height of 17 meters. How much work is done during the lifting?

(how do we get to the answer as well)

2 Answers

5 votes

Answer: 1500 J

Explanation: work done is the product of force and its perpendicular distance.

Force is mass multiplied to gravity.

9 kg x 9.8 m/s² x 17 m = 1500 J

User Michel Mesquita
by
5.8k points
5 votes

Answer:

1,530J

Step-by-step explanation:

work done = energy expended = mgh

work done = 9*10*17 = 1,530J