Answer:
Material price variance = $954 favorable
Material quantity variance = $9,275 unfavorable
Step-by-step explanation:
The computation is shown below:
Material price variance
= Actual Quantity × (Standard Price - Actual Price)
= 9,540 pounds of material × ($2.5 - $2.4)
= 9,540 pounds of material × $0.11
= $954 favorable
Material quantity variance
= Standard Price × (Standard Quantity - Actual Quantity)
= $2.5 × (1,060 units × 5.5 pounds - 9,540)
= $2.5 × (5,830 - 9,540 )
= $2.5 × 3,710
= $9,275 unfavorable