The management in Exercise 43 requires that a new employee be producing at least 20 units per day after 30 days on the job.
(a) Find a learning curve model that describes this minimum requirement.
(b) Find the number of days before a minimal achiever is producing 25 units per day.

1 Answer

3 votes

Final answer:

To model the minimum requirement of producing 20 units per day after 30 days, we can use the power-law learning curve model. Plug in the values to find the constants, and then use the model to predict the number of days to reach 25 units per day.

Step-by-step explanation:

To find a learning curve model that describes the minimum requirement of producing at least 20 units per day after 30 days, we can use the power-law learning curve model. The formula for the power-law learning curve model is:

Y = a * X^b

Where Y is the output, X is the cumulative production units, and a and b are constants. In this case, we know that after 30 days, the minimum requirement is 20 units, so we can plug in these values into the equation to solve for a and b. Once we have the values for a and b, we can use them to predict the number of days it would take for a minimal achiever to produce 25 units per day.

User Rokkuchan
by
8.0k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories