Answer:
$840
Step-by-step explanation:
Data provided in the question:
Direct material at $2.80 per pound = 3 pounds
Standard cost of direct material = $8.40
Direct labor at $7.40 per hour = 6 hours
Standard direct labour cost = $44.40
Actual Units produced 6,600 units
Actual Direct material purchased 26,200 pounds at $3.00 = $78,600
Actual Direct material used 19,500 pounds at $3.00 = 58,500
Actual Direct labor 40,700 hours at $7.20 = 293,040
Now,
Direct material quantity variance
= (Actual quantity used - Standard quantity used) × Standard price
= [19,500 - (6,600 × 3)] × $2.8
= (19,500 - 19,800) × $2.8
= $2.8 × 300 [ignoring negative sign]
= $840 (Favorable as actual quantity used is less than the standard quantity)