212k views
0 votes
LO 4.7In a job order cost system, overhead applied is debited to which account?

work in process inventory
finished goods inventory
manufacturing overhead
cost of goods sold

1 Answer

1 vote

Answer:

work in process inventory

Step-by-step explanation:

The journal entry to record overhead applied is shown below:

Work in progress inventory A/c Dr XXXXX

To Factory overhead A/c XXXXX

(Being applied overhead is recorded)

And, the journal entry to record over applied is presented below:

Manufacturing overhead A/c Dr XXXXX

To Cost of Goods sold A/c XXXXX

(Being over-applied overhead is recorded)

Over applied is come when actual overhead based on predetermined rate is more than the actual manufacturing overhead

User Alexandre Juma
by
8.0k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.