Answer:
Step-by-step explanation:
The journal entry is shown below:
Work in process A/c - shaping department Dr $35,000
Work in process A/c - packaging department Dr $25,000
To Manufacturing overhead A/c $60,000
(Being apply overhead to the manufacturing departments is recorded)
The computation is shown below:
For shaping department
= 3,500 machine hours × $10 per machine hour
= $35,000
For Packaging department
= 2,500 machine hours × $10 per machine hour
= $25,000