LO 6.3Rocks Industries has identified three different activities as cost drivers: machine setups, machine hours, and inspections. The overhead and estimated usage are:



Compute the overhead rate for each activity.

User Nuncjo
by
5.4k points

1 Answer

2 votes

Question:

EB8.

LO 6.3Rocks Industries has identified three different activities as cost drivers: machine setups, machine hours, and inspections. The overhead and estimated usage are:

Activity Overhead per Activity Annual Usage

Machine Setups $75,000 6,000

Machine Hours $85,002 5,484

Inspections $70,000 20,000

Compute the overhead rate for each activity.

Answer:

Following two steps helps in finding the Overhead Rate for every activity.

Step 1: Identify cost pools and their relevant cost drivers.

Cost Driver Cost pool

Machine Setups $75,000

Machine Hrs $85,002

Inspection $70,000

Step 2: Calculate Overhead rate for each activity

Overhead Rate= Cost pool / total units of relevant cost driver consumed

Now just put the values in the formula and compute overhead rate for each overhead.

Overhead Rate for machine setup=$75,000 / 6,000 total setups= $12.5 per setup

Overhead Rate for Machine cost=$85,002 / 5,484 total Machine hrs= $15.5 per machine hr

Overhead Rate for Inspection cost=$70,000 / 20,000 total Inspections= $3.5 per Inspection