Answer:
$40
Step-by-step explanation:
Overhead per machine hour = Overhead ÷ 250,000 machine hours
= $750,000 ÷ 250,000
= $3
Cost of each unit:
= Direct material + Direct labor + Overhead
= $14 + $20 + (machine hours per unit × Overhead per machine hour)
= $14 + $20 + (2 × $3)
= $40
Therefore, the cost of each unit produced is $40.