Who is usually responsible for site plans, subdivision plans, building permits, and ruling on zoning issues?

A. The state legislature
B. The planning commission
C. The zoning board of appeals
D. The city manager

1 Answer

3 votes

Answer:

The correct option is B: The planning commission

Step-by-step explanation:

The role played by the planning commission in the planning process are three-faced. First, it functions as an advisor to the governing body on all matters pertaining to planning and development. Secondly, it ensures the implementation of the general plan, and thirdly it makes the final decisions for proposals. However, the planning commission is involved for other activities such as subdivision plans, building permits, and ruling on zoning issues.