Which of the following strategies should the Government NOT consider during IP implementation?

a. Consider data rights as a ?priced option? to the contract.
b. Negotiate data rights after a contractor has been notified of selection.
c. Outline the Government`s data rights needs in the RFP.
d. Make technical data rights a source selection criterion

User A Magoon
by
8.3k points

1 Answer

4 votes

Answer:

Correct answer is (b). Negotiate data rights after a contractor has been notified of selection.

Step-by-step explanation:

During IP implementation, it is expedient for government to outline and negotiate the data before selection and notification of contractor to ensure effective planning.