It is helpful to list requirements and supporting information in a requirements traceability matrix. When requirements are complete, they should meet all of these criteria EXCEPT:a. identified with the stakeholder who needs itb. assigned to a team member who will be the requirement ownerc. measurable, so that the value and completion can be verifiedd. prioritized so tradeoff decisions can be made if necessary

User Rohrbs
by
5.6k points

1 Answer

4 votes

Answer:

The correct option is B

Step-by-step explanation:

It is of great importance for the requirements and supporting information in a requirements traceability matrix to be listed. Upon fulfilling all requirements, there are certain criteria that must be met. The requirements must be prioritized, measurable, and must be identified with a stakeholder who has need for it. Thus, the only option that is not a requirement is that it is to be assigned to a requirement owner.