If your procurement budget request did not provide for buying a whole number of useable end items, this would be a violation of which funding policy?

User Gtu
by
5.4k points

1 Answer

4 votes

Answer:

Full funding policy.

Step-by-step explanation:

This would be a violation of Full funding policy.

Full funding strategy is a federal budgeting requirement implemented by Congress in the 1950s on the Department of Defense (DOD) that mandates all acquisition expenses of a weapons or piece of military equipment to be financed in the year the object is procured. Hence in the above example there is violation of Full funding strategy.