Solution:
Net Present Worth (NPW) ($ Million) = - 2,000 + 100 x PVIFA(5%, 30)
= - 2,000 + 100 x 15.3725**
= - 2,000 + 1,537.25
= - 462.75
Since NPW < 0, the project is financially not viable.