Answer:
4 workers
Explanation:
A group of 9 workers was assigned to paint the walls in a house, which could be completed in 48 hours. Then 1 worker will complete the whole job in
hours.
If 1 worker completes the whole work in 432 hours, then he completes
of the work per hour.
9 workers complete
of work per hour and complete
of work in 8 hours.
of work left.
This could be completed by n workers in 72 hours, so
9 - 5 = 4 workers left the team.