Answer:
A = 8hrs
H = 3hrs
M = 0hrs
Explanation:
Let a be the working hours of plant A.
Let b be the working hours of plant H.
Let c be the working hours of plant M.
∴ Hours of plants A,H,M are a,b,c respectively.
We have to minimize the cost of production, Z = 60a + 92b + 140c
Regular ice cream: 40a + 20b + 40c = 350
Deluxe ice cream: 20a + 40b +40c =240
Where a>=0, b>=0, c>=0
So, by solving this, a= 7.67, b= 2.77,c= 0
So working hours of plant A = 8 hrs
Working hours of plant H = 3 hrs
Working hours of plant M = 0 hrs