​Fulkron, Inc. provides the following data taken from its third quarter​ budget: Jul Aug Sep Cash collections 67,000 $33,000 $42,000 Cash​ payments: Purchases of direct materials 33,000 34,000 30,000Operating expenses 12,000 20,000 24,000Capital expenditures 0 33,000 6,000The cash balance on June 30 is projected to be $12,000.Based on the above​ data, calculate the shortfall the company is projected to have at the end of August.

User Vlox
by
3.8k points

1 Answer

4 votes

Answer:

-$20,000 short fall

Step-by-step explanation:

July:

Total cash available:

= Cash balance + Cash collections

= $12,000 + $67,000

= $79,000

End cash:

= Total cash available - Cash payments

= $79,000 - (33,000 + 12,000)

= $79,000 - $45,000

= $34,000

August:

Total cash available:

= Cash balance + Cash collections

= $34,000 + $33,000

= $67,000

End cash:

= Total cash available - Cash payments

= $67,000 - (34,000 + 20,000 + 33,000)

= $67,000 - $87,000

= -$20,000 (Short fall)