help please someonee Two teams working together can finish a job in 8 days. if the first team works alone for two days and the second team works alone for 5 days, 5/8 of the total work still remains. How many days will it take each team to finish the work alone?

2 Answers

2 votes
The first team should be 16 days and the second team should be 24
User Mrkwjc
by
3.5k points
3 votes

Answer:

It'll take the first team 16 days and the second team 24 days to finish the work alone