Ratio. Proportion and many method d) 15 workers were employed to complete a piece of work in 36 days. How many more workers should be added to complete the work in 30 days?​

1 Answer

4 votes

Answer:

Explanation:

total of 15(36) = 540 person•hours was used

540 / 30 = 18 people

18 - 15 = 3 people need to be added