Help me please i really need it please answer it correctly,i need solution.​

Help me please i really need it please answer it correctly,i need solution.​-example-1
User Johhny B
by
3.3k points

2 Answers

6 votes

Answer:

my calculations are saying 12.8

Step-by-step explanation:

32 men x 6 days / 15 men

User Sandy Vanderbleek
by
3.2k points
4 votes

Answer: 12.8 days

Step-by-step explanation:

x = number of days

y = number of men

The values of x and y are inversely proportional. This means as x goes up, y goes down, and vice versa. If you hire more men, then it will take less days. Having fewer workers means it takes more time.

The equation that connects the two variables together is y = 192/x. If we plugged in x = 6, then we'd get y = 32.

Plug in y = 15 and solve for x and you should get x = 12.8

It takes 12.8 days for 15 men to do the job.