2. Twenty machines can embroider 1000 sweaters in 5 days.

a. In how many days can 10 machines embroider the same 2000 sweaters?
b. How many machines would needed to embroider 5000 sweaters in 10 days?

User Laymanje
by
8.0k points

1 Answer

6 votes

Answer:

a) 20 days

b) 50 machines