A construction company needs to remove 4 3/4 tons of dirt from a construction site. they can remove 5/6 tons of dirt each hour. What os the total number of hours will take to remove the dirt? ( write your answer as a mixed number in simplest form )

1 Answer

6 votes

Answer:

5.7 hours

Explanation:

Divide 4 3/4 by 5/6 hope this helps! :)