If Andrew can paint 1 house in 4 days can he paint 9 houses in 27 days

User Xhudik
by
7.6k points

1 Answer

5 votes

Explanation:

since this is a linear work and function, no, he cannot.

1 house in 4 days.

9 houses then in 9×4 = 36 days.