Patrick Enterprises recently installed a parking lot. The paving costs were $38,750, and the lighting costs were $20,000. In addition, the company entered into a $1,000 annual agreement with Romero Cleaning to maintain the parking lot. For what amount should Patrick Enterprises debit the land improvements account when the parking lot is completed

User David Berg
by
4.6k points

1 Answer

1 vote

Answer:$58,750