A man can do a piece of work in 20 days.

i. how much work does he do in 1 day
ii. how much work does he do in 5 days
iii. if he leaves the work after 10 days,how much work is left to do?

pls plssss help​​

1 Answer

2 votes
  • Answer:

Explanation:

i) A man can do a piece of work in 20day.

So, in 1 day man can do 1/20 piece of work.

ii) In 1 day man can do 1/20 piece of work

So In 5 days man can do 1/20*5

In 5 day man can do 1/4 piece of work

iii) a man can do 1/20 piece of work in 1 day

so in 10 day a man can do 1/20*10= 1/2 work

1/2 work is left to do.

Hope this helps.