It takes 6 boys 15 days to clean a field on a small plot. How long will it take 8 boys?​

User Putxe
by
3.6k points

1 Answer

6 votes
6 votes

Answer:

20 days

Explanation:

Time to clean field for 6 boys=15days

Time to clean field for 1 boy=15/6 days

Time to clean field for 8 boys=15/6 × 8 days

Time to clean field for 8 boys=120/6 days

Answer=20 days

Note:if you need to ask any question please let me know.