In 6 days, a group of workers can plant 30 acres.
What is their rate in acres per day?

User Hrv
by
8.6k points

1 Answer

0 votes

Answer:

5 acres per day

Explanation:

Since it is 30 for 6 days, divide 30 by 6 to get how many per day