A can do a piece of work in 10 days and B can do it 15 days. If both of them are working together, half of the work can be finished in?
Here we find,LCM of 10 and 15 is 30.
- A can do ( 1 /10 th ) of the work in one day Or, ( 3/30th ).
- B can do ( 1/15th ) of the work in one day ( or 2/30th ).
Working together, A and B can do
- = 1/6 th of the work in one day.
So, they would require 30/5 or 6 days to complete the task.