6m=40hours
1m=40×6h
=240hours
4m=240÷4
=60 hours
divide 60 by 8
=7.5 days
thus,
4 men take 2 and 1/2 day more to complete the job.
Answer: 2 1/2days
9.4m questions
12.1m answers