151k views
3 votes
A piece of work can be done by 24 men in 15 days.in how many days can 18 men do the same work?​

1 Answer

4 votes

18 people is 25% less people so will take 25% longer

25% of 15 is 3.75

3.75+ 15 = 18.75 days ?