Answer:
Predetermined manufacturing overhead rate= $1.25 per machine hour
Step-by-step explanation:
Giving the following information:
Estimated manufacturing overhead= $530,850
Total estimated machine hours= 64,247*2 + 98,875*3= 425,119
To calculate the predetermined manufacturing overhead rate we need to use the following formula:
Predetermined manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base
Predetermined manufacturing overhead rate= 530,850 / 425,119
Predetermined manufacturing overhead rate= $1.25 per machine hour