Answer:
1. top-down
2. apportion
Step-by-step explanation:
Based on the manufacturing industry standards, Project managers typically use TOP-DOWN also called analogous estimating or the APPORTION method when there is a past history of similar projects and rough-cut estimates are needed for strategic purposes two to five years out because, as estimating methods go, it is faster and less expensive.